Ground-mounted photovoltaic arrays at the 30 MW Butimanu solar project in Romania

RAM project · Renewable energy · Romania · 2026

Butimanu solar park — 30 MW installation works

RAM was subcontracted for a defined mechanical and electrical execution scope on a 30 MW photovoltaic project in Butimanu, Romania, mobilising 40 specialist installers and two site supervisors.

Coordinated mechanical and electrical installation

RAM supported the Butimanu photovoltaic project as a mechanical and electrical installation subcontractor. The agreed work package combined the assembly of ground-mounted steel structures, photovoltaic module installation and electrical installation activities across coordinated site work fronts.

The project required disciplined sequencing between pile alignment, structural assembly, module positioning and the installation of protected cable routes and electrical equipment. RAM mobilised separate structure and module teams under dedicated supervision so that each phase could progress in line with the main contractor’s programme and site requirements.

The photographs in this project record are real images from the Butimanu site. They document the work from driven posts and galvanized support frames through to completed module rows, underground conduits and equipment installed beneath the arrays.

ProjectButimanu photovoltaic park
Capacity30 MW
RAM roleMechanical and electrical installation subcontractor
LocationButimanu, Dambovita County, Romania
Site team42 people
Installation scopeStructures, PV modules, cable routes and equipment mounting

Mobilised workforce

A 42-person team organised around the installation sequence

20

Mounting-structure installers

Dedicated to pile-line preparation, structural assembly, alignment and completion of the ground-mounted support system.

20

PV module installers

Focused on module positioning, alignment and secure installation across the completed photovoltaic support structures.

2

Site supervisors

Coordinating work fronts, installation quality, daily priorities and interfaces with the main contractor’s site programme.

Execution scope

Practical delivery across four linked work fronts

01

Ground-mount structure installation

Positioning, assembly and alignment of galvanized steel support structures for the photovoltaic arrays.

02

Photovoltaic module installation

Positioning, alignment and securing of PV modules on completed structures in accordance with the construction sequence.

03

Cable routes and protective conduits

Installation support for underground cable routes and protective conduits coordinated with the mechanical work fronts.

04

Electrical equipment mounting

Mounting and routing activities for electrical enclosures and associated equipment within the agreed subcontracted scope.

Need a coordinated solar installation workforce?

Share the project location, defined work package, available drawings, programme and required mechanical or electrical trades. RAM will review the interfaces and propose a practical execution or workforce solution.

Discuss your solar projectGreen energy services

Project verification

Butimanu project facts

What is the installed capacity of the Butimanu solar project?

The documented Butimanu photovoltaic project in Romania has a capacity of 30 MW.

How large was the RAM team at Butimanu?

RAM deployed a 42-person site team: 20 mounting-structure installers, 20 PV module installers and two site supervisors.

What work did RAM perform at Butimanu?

The documented scope included ground-mount structure assembly, photovoltaic module installation, cable routes and equipment mounting.