Qualifying a welding procedure and qualifying a welder are separate tasks. The paperwork for each answers a different question. This guide explains WPS vs WPQR in plain terms: what each document does, how welder qualification sits next to them, and what a QA/QC lead or welding coordinator can check before a welder starts on a production joint.
This guide focuses on the ISO framework and the welding procedure test route in ISO 15614-1. Other codes, including ASME, use their own qualification rules; do not treat records as interchangeable without checking the governing requirements.
For work using the qualification route discussed here, check three types of document together:
The ISO series discussed here calls the record a WPQR (welding procedure qualification record), and the general rules for the whole series sit in ISO 15607:2019. It states that welding procedures are qualified by conforming to one or more WPQRs. It also assumes that welding procedure specifications are used in production by competent welders qualified to the relevant part of ISO 9606, or by competent operators qualified to ISO 14732.
So the procedure is qualified, the person is qualified, and production needs both.
For arc welding, ISO 15609-1:2019 sets the content of a WPS. It specifies requirements for the content of welding procedure specifications for arc welding processes, and the variables it lists are those influencing the quality of the welded joint. The WPS is the instruction for the work front, not proof that the procedure works.
For the route discussed here, the evidence comes from a welding procedure test. For arc and gas welding of steels, and arc welding of nickel and nickel alloys, the test standard is ISO 15614-1:2017. It specifies how a preliminary welding procedure specification is qualified by welding procedure tests, and it applies to production welding, repair welding and build-up welding. Its abstract states the primary purpose: to show that the joining process can produce joints with the required mechanical properties for the intended application.
Put together, the sequence runs like this:
A procedure test is not the only qualification route. Depending on the application standard and contract, the applicable framework may also permit routes based on tested consumables, previous welding experience, a standard welding procedure or a pre-production welding test. The welding coordinator should confirm which route the project permits for the actual work.
ISO 15614-1 gives two levels of procedure test. In level 2, the extent of testing is greater and the ranges of qualification are more restrictive than in level 1. A level 2 test automatically qualifies for level 1, but not the other way round. When no level is specified in a contract or application standard, all the requirements of level 2 apply. Check at contract review which level the specification calls for, and whether the existing WPQRs meet it.
A qualified procedure says nothing about the person holding the torch. That is the job of ISO 9606-1:2012, which specifies the requirements for qualification testing of welders for fusion welding of steels. It assesses the person's practical skill in controlling the welding equipment and producing an acceptable test weld.
Two points from its scope matter on site:
So a welder with a valid certificate may still lack clearance for a joint outside the qualification range. A qualified WPS also does not make an unqualified welder acceptable. The two checks run side by side.
| Document | WPS | WPQR | Welder qualification |
|---|---|---|---|
| What it is | How the weld is made | Qualification basis for the procedure | Qualification of the individual welder |
| Standard used here | ISO 15609-1:2019 (content) | ISO 15614-1:2017 (procedure test) | ISO 9606-1:2012 (welder test) |
| Question answered | How? | Does the procedure give the required properties? | Can this welder make an acceptable weld? |
Before a welder starts on a production joint, a QA/QC lead or welding coordinator can work through four points:
Check the editions and amendments required by the contract, and review any transition provisions before relying on an older qualification. A newer publication does not, by itself, establish whether an existing record is acceptable for a particular project. That decision requires the governing standard and the project requirements.
RAM starts with the work the crew will perform, not only with a request for a number of welders. We review the information made available for the assignment: the governing standard and project specification, WPS and supporting WPQR where applicable, welding process, base material, joint type, thickness and diameter range, welding position, work environment and the records the client expects before mobilisation.
We then compare those requirements with each proposed welder’s qualification range, relevant practical experience and current documentation. This prevents a common project problem: mobilising a capable welder whose certificate does not cover the actual process, material group, position or dimensional range required for the joint.
If an otherwise suitable welder does not yet hold the qualification required for the assignment, or if the client requires a project-specific test, RAM can coordinate the candidate, documentation and test timing at the client’s request. Agree the test conditions, WPS or test instruction, acceptance route and required records against the governing standard and contract. Examination, acceptance and certificate issue remain with the competent examiner, examining body or client authority required by the project; RAM does not present itself as the independent certification body.
Under workforce supply, the client directs welding execution and retains control of the production WPS, inspection and acceptance unless the contract says otherwise. Under technical subcontracting, RAM can organise the trades, supervision and coordination around a defined scope, with responsibilities, deliverables and acceptance criteria agreed before work starts.
In practical project language, welding procedure “homologation” usually refers to qualifying and approving a welding procedure against the governing standard and contract requirements. Under the ISO test route described here, a preliminary WPS is supported by a welding procedure test and the qualified result is recorded in a WPQR. For production, repair or build-up welding, the qualification range and any client or classification requirements still have to cover the actual joint. The term does not replace a check of the applicable standard, procedure and records.
Yes. At the client’s request, RAM can select suitable welders, review their existing qualification coverage and coordinate a required practical test, qualification or revalidation process before mobilisation. The examination and certificate must be completed or accepted by the competent examiner, examining body or client authority specified for the project. Send RAM the welding process, material, joint and range information, positions, WPS where available, project location and mobilisation date so the correct route can be discussed.
No. The WPQR records the qualification basis. The approved WPS gives the instructions and variables for production welding.
No. Procedure qualification and individual welder qualification are separate checks. Production requires both to cover the assigned work.
Confirm the correct WPS revision, supporting WPQR, welder qualification range, validity and the editions required by the contract.
We use optional Google Analytics and Google advertising technologies to measure how this site is used, understand enquiries and improve our services. These optional cookies and consent signals are activated only after you accept. If you reject, Google receives limited cookieless measurement signals. You can change your choice at any time. Form contents are never sent. Read our Privacy Policy.