A turnaround packs a large block of maintenance into a short, fixed window, and the plan only works if the right trades are on the right work fronts when the plant releases them. This guide explains how turnaround manpower planning works in practice: building headcount from the scope, planning shifts without creating fatigue, and agreeing what contractor crews need before they mobilise.
It is tempting to open a shutdown plan with one question: how many people do we need? Headcount is a result, not a starting point. It comes out of the work list, the sequence, the access and the length of the window.
EU-OSHA's Factsheet 88 on safe maintenance describes maintenance as a process that starts before the task begins and ends when the responsible team has checked, signed off and documented the work. For the planning stage it lists what the risk assessment must consider, including:
Read as a manpower checklist, the order is clear: skills and numbers come after scope and hazards, and roles and reporting lines belong in the plan from day one.
A practical sequence for turning the work list into a crew plan:
Then test each peak against reality: can the work front physically hold that many people, and can supervision, permit issuing and inspection keep up?
When a turnaround runs day and night shifts, manpower planning meets fatigue risk directly. HSE UK's guidance on fatigue places the legal duty to manage fatigue risks on employers and names excessive working time and poorly designed shift patterns as causes. It says night workers are particularly at risk.
HSE lists the shift design factors to assess: workload, the work activity, shift timing and duration, direction of rotation, and the number and length of breaks. It recommends a policy that sets limits on working hours, overtime and shift-swapping, and a system to record them. It also notes that problems with overtime and shift-swapping may indicate inadequate resource allocation and staffing levels.
For a turnaround project manager, sustained overtime is a signal to reassess the plan. Review workload, sequencing, staffing and supervision before accepting a programme that relies on long hours. Working time rules differ by country. Check them for each site and each employer.
HSE's page on workload says employers should reconsider workload during unusual activities such as "campaign maintenance", and that it may matter more temporarily during peaks. It adds that a staffing assessment should look not just at the number of people but at how they work.
The method HSE points to is task analysis: understand exactly what staff need to do and when, covering physical and mental workload, with the workforce involved. On a turnaround, that has to include the plant's own operators and permit issuers. If isolations and permits fall behind, every contractor trade waits at once.
EU-OSHA stresses that employers should train workers, including subcontractors, and familiarise them with established procedures. Workers should follow the work plan even under time pressure. It also warns that exceeding the scope of one's own skills and competence may result in a very serious accident. Those points turn into a short list to settle with each contractor:
| Item | What to agree |
|---|---|
| Scope | Which work packages the crew covers, and the interfaces with other contractors |
| Qualifications | Certificates and, for welders, qualification ranges checked against the project's procedures |
| Supervision | Who directs the crew, the chain of command and who receives problem reports |
| Shifts and hours | Shift pattern, limits on overtime and who records hours and how |
| Induction | Site induction and permit procedures completed before the first shift |
| Dates | Arrival before the work front is released, and a planned release as packages close |
RAM plans shutdown crews around the work scope, outage window and available work fronts. RAM's records in this sector include welding on an offshore project in the Dutch sector of the North Sea and pipe fitting at an energy-utility workshop in the Netherlands, and RAM has a project record at an oil terminal in Frederikshavn, Denmark. These records show relevant industrial settings; each shutdown still needs a scope-specific crew plan.
Before anyone mobilises, RAM follows four steps published on its oil and gas services page:
For welding scopes, RAM checks each proposed welder's qualification range, relevant experience and required documentation against the project requirements. The WPS sets how to make the weld, the WPQR is the qualification basis for that procedure, and the welder's qualification is a separate requirement. A welder whose range does not cover the scope may not be accepted, which can delay a work front, particularly in a shutdown or turnaround window.
The two delivery models split responsibility differently. Under workforce solutions, welders, pipefitters, fitters, electricians or complete crews join the client's organisation: RAM handles employment, documentation, mobilisation and workforce administration, while the client directs the work and keeps control of scope and day-to-day execution. Under technical subcontracting, RAM organises the trades, supervision and coordination for a defined package around the deliverables, interfaces and acceptance criteria in the contract.
If you are building the manpower plan for a shutdown, send the scope, the dates of the window and the disciplines involved through the contact page.
We use optional Google Analytics and Google advertising technologies to measure how this site is used, understand enquiries and improve our services. These optional cookies and consent signals are activated only after you accept. If you reject, Google receives limited cookieless measurement signals. You can change your choice at any time. Form contents are never sent. Read our Privacy Policy.