An offshore installation that stops producing cannot simply be left where it stands. In the North East Atlantic, the offshore decommissioning process runs from a cessation plan, through safety consents and removal at sea, to dismantling in a yard ashore. This guide walks through those phases, the documents each one needs under OSPAR, UK and Norwegian rules, and what they mean for a project manager planning the work.
This overview focuses on installation removal and the yard phase. Well abandonment, pipelines, subsea infrastructure and environmental obligations require their own project-specific assessment. Agree those boundaries before defining a contractor’s work package.
OSPAR Decision 98/3, as amended by Decision 2024/01, governs disposal of disused offshore installations in the OSPAR maritime area. Its starting point is a prohibition on dumping or leaving installations wholly or partly in place.
However, derogations require a competent authority’s assessment and consultation with the other Contracting Parties. The decision sets specific conditions for eligible steel footings and concrete installations, and a separate route for exceptional, unforeseen circumstances. These are controlled exceptions, not an assumption that an installation can remain at sea. Use the consolidated decision and the project’s approved disposal solution when planning removal.
In Norway, the regulations to the Petroleum Act require a decommissioning plan with a disposal part and an impact assessment. The plan goes to the Ministry, with copies to the Norwegian Offshore Directorate and the Norwegian Ocean Industry Authority. The disposal part addresses alternatives, the recommended solution and its proposed schedule.
In the UK, owners submit a decommissioning programme under the Petroleum Act 1998. OPRED oversees compliance with these requirements. The programme and its approvals establish the scope and sequence; a contractor’s mobilisation plan does not replace them.
An approved plan is not permission to start cutting. In the UK, regulation 20 of the Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015 says a fixed installation in external waters must not be dismantled until the operator has sent a revised safety case to the competent authority at least three months before dismantling starts, unless the authority specifies a shorter period, and the authority has accepted it.
In Norway, Havtil identifies disposal, removal and relocation of a facility as activities requiring consent. However, that consent does not transfer the operator’s responsibility for safe execution to the regulator or the workforce provider.
This is the marine phase: the approved lifting, maritime and subsea operations move the installation towards its agreed destination. The removal engineer and marine contractors determine the lift strategy, structural preparation, vessel requirements and operational limits.
For a supporting technical crew, define the exact work areas, preparation tasks, supervision and handover points. Welding or pipefitting capability alone does not establish responsibility for offshore removal engineering or heavy-lift operations.
At the receiving yard, the work changes to controlled dismantling and material handling. Before assigning people, confirm the asset’s condition, released work areas, hazardous-material information, structural sequence and the interfaces with lifting and waste contractors.
Where UK construction legislation applies, CDM 2015 regulations 19 and 20 address structural stability and planned dismantling. HSE’s demolition guidance emphasises competent planning and a documented method. Establish the applicable regime for the particular asset and yard; vessel dismantling may involve different arrangements.
In addition, the package should identify who releases each area, who directs the technical crew, which operations need specialist contractors, and what records the yard requires at handover. Country-specific rules and the approved project plan determine the detailed requirements.
RAM’s offshore portfolio includes a decommissioning-yard project in Haugesund, Norway. For a comparable assignment, start with the specific onshore work package, required trades and the yard’s supervision and permit arrangements. See our offshore workforce and technical project support.
For offshore projects, RAM supplies qualified technical personnel and delivers defined technical subcontracting scopes. The trades across both models include welding and fabrication, piping and pipefitting, structural steel and erection, mechanical and electrical installation, and site supervision. The two models split responsibility differently:
Before anyone mobilises, RAM works through four steps. First, understand the work: scope, drawings and specifications where available, programme, disciplines and site conditions, with headcount coming out of that conversation. Second, match capability to the task: process, position, material and previous working environment (see welding and fabrication). Third, check qualifications and documentation against what the project asks for. Fourth, agree scope, supervision, interfaces and deliverables before anyone travels. On a dismantling project, settling those interfaces early matters, because each contractor must understand the work it controls and the interfaces it hands over.
If you are planning the yard phase of a decommissioning project, send RAM the asset, the yard and the work window.
The guide covers the decommissioning plan, safety consent before removal, removal at sea and dismantling ashore. It focuses on installation removal and the yard phase. Well abandonment, pipelines and subsea infrastructure need their own project-specific assessment.
OSPAR Decision 98/3, as amended by Decision 2024/01, starts from a prohibition on dumping or leaving disused installations wholly or partly in place. Any eligible derogation or exceptional route requires the prescribed assessment, consultation and authority decision. Do not assume an exception applies to a project.
Under regulation 20 of the 2015 Safety Case Regulations, the revised safety case must reach the competent authority at least three months before dismantling starts, unless the authority sets a shorter period. The authority must accept it before dismantling.
Establish the applicable regime for the asset and yard. Where CDM 2015 applies, the work needs planned dismantling arrangements, competent people and controls for structural stability. Vessel dismantling may involve different arrangements.
We use optional Google Analytics and Google advertising technologies to measure how this site is used, understand enquiries and improve our services. These optional cookies and consent signals are activated only after you accept. If you reject, Google receives limited cookieless measurement signals. You can change your choice at any time. Form contents are never sent. Read our Privacy Policy.